BENJI CIRCLE FLY OVER TO BE COMPLETED BY NOVEMBER


Vijayawada, June 13, (way2newstv.in)
The benchmark of the benji circle, which has completed over 45 per cent so far, has four parallel tasks in line with the road map designed to be completed by the end of November. Tasks are going to be faster than ever before. Construction of gaders, construction of balance pillars, approach tasks, setting up pillars near benji circle were primarily initiated. Every day, we decided to set up two guards. With two huge cranes at night, no one is causing gamblers to bother. It looks new in the morning. At present there is a Gadder arrangement on P1-P2 Pillars at SVS Kalyana Mandapam. From here, we will gradually arrange gadders on the pillars up to Ramesh Hospital Junction respectively. Gadders are being brought to benzarkal on trolleys according to the root plan set out from the Casting Depot in Pennamalur. The traffic is restricted to one side in the night at 11 o'clock. Highway one way. There is no trouble for traffic.


 BENJI CIRCLE FLY OVER TO BE COMPLETED BY NOVEMBER  
 Gadder is set between 1-3 hours after midnight. There are a total of 240 gurders to be set up for benji circulation construction. There should be a total of 49 Pillars to be built on  flyover. So far, 30 pools have been set up. There are 19 children at different stages. These are completed by the end of July. Benji fly over approach  has also begin. At the SVS junction, Ramesh has to set up two approaches after passing the hospitals. The soil was flattened to place the approaches in two places. Approach works have been initiated from the SVS Junction. At the benji circulation, barricading will be set up to establish 9 and 10 pellets. NH and police superintendents have been examined for the creation of the barricading system. Two days, the barricading will be set up and the pedals will be started.

No comments:

Post a Comment